|
United States Environmental
Protection Agency Region
V POLLUTION REPORT |
| Date: |
Wednesday, October 24, 2007 |
| From: |
James Augustyn/Brian Schlieger, On-Scene
Coordinator |
| To: |
Jason El-Zein, USEPA |
David Chung, OSWER |
|
Al Taylor, MDEQ |
NRC Duty Officer, National Response
Center |
|
Cheryl Howe, MDEQ |
Rick Karl, USEPA |
|
Mark Johnson, U.S. EPA
R5 |
Todd Konechne, Dow Chemical
Company |
|
Jeff Cahn, USEPA |
Jim Sygo,
MDEQ |
|
Subject: |
Removal Action Tittabawassee
River Reach O Midland, MI Latitude:
43.5522 Longitude: -84.1714 |
| POLREP No.: |
10 |
Site #: |
B5KF |
| Reporting Period: |
10/18/07 to 10/24/07 |
D.O. #: |
|
| Start Date: |
8/13/2007 |
Response Authority: |
CERCLA |
| Mob Date: |
8/13/2007 |
Response Type: |
Time-Critical |
| Completion Date: |
|
NPL Status: |
Non NPL |
| CERCLIS ID #: |
MID980994354 |
Incident Category: |
Removal Action |
| RCRIS ID #: |
|
Contract # |
|
|
On June 27, 2007, U.S. EPA ordered The Dow Chemical Company (Dow)
to negotiate an Administrative Order on Consent, to address removal
of extremely elevated levels of dioxin-contaminated sediment from
within Reach O of the Tittabawassee River near Midland,
Michigan. Dow agreed to the terms of the Order and on
July 12, 2007, the Order was signed by the Regional Administrator
and Dow. For additional background information please see
the site profile.
On-Scene Coordinator (OSC) Jim Augustyn is
providing oversight with assistance from U.S. EPA’s START
Contractor, Weston Solutions, Inc. |
|
The following tasks are currently on
going:
• The decontamination and
demobilization of the heavy
equipment. • The importing and application
of topsoil. • The restoration of the haul
access road along the river
embankment. • Planting of native plants
along disturbed section of river bank
To view a map that
depicts current site progress, please visit the Document Section of
this website and open the document titled "Site features
map".
The following tasks have been completed by Dow
contractors during the period from October 18 – 31,
2007:
Thursday, October 18: Work activities suspended due to
severe weather conditions.
Friday, October 19: Dow completed
the removal of all sheet piling from the river. Other work
activities included the decontamination and demobilization of
barges, sheet piling and heavy equipment from the Site. Shoreline
stabilization and restoration activities started at the RMU 1/2
access ramp.
Saturday, October 20 and Sunday, October 21: No
Site operations conducted.
Monday, October 22: Dow continued
the dismantling, decontamination and demobilization of heavy
equipment from the Site. Stabilization and restoration activities of
the river shoreline continued at the RMU 1/2 access
ramp.
Tuesday, October 23: Site activities
included: the transportation of excavated logs to the Salzburg
Landfill for staging purposes, continued shoreline stabilization
activities at the RMU 1/2 and RMU 5 access ramps, and continued
dismantling and demobilization of heavy equipment from the Site.
Dow’s contractor also began discharging the treated wastewater
(Batch #4) to the Tittabawassee River. The dewatering pad will not
be dismantled as part of this scope of work. The dewatering pad will
remain intact for possible future use.
Wednesday, October 24:
Dow continued the stabilization and restoration activities of the
river shoreline and the access haul road along the top of the river
embankment. Other restoration activities included the importing and
application of topsoil, straw bails, and straw
matting.
Thursday, October 25 and Friday, October 26: Dow
continued the stabilization and restoration activities of the river
shoreline and the access haul road along the top of the river
embankment and continued demobilization of some heavy equipment from
the Site.
Saturday, October 27 and Sunday, October 28: No
Site operations conducted.
Monday, October 29: The haul road
sand removed from along the top of the river embankment was
transported to the Salzburg Landfill for disposal. Approximately 4
inches of sand backfill material was also removed from the
dewatering pad and transported to the Salzburg Landfill for
disposal. Since all work activities within the Tittabawassee River
has been completed, the upstream and downstream turbidity meters
were removed from the river.
Tuesday, October
30: Surface soil samples were collected from post
excavation area inside the dewatering pad to identify the presence
of any residual contaminated sediment. Dow continued the
stabilization and restoration activities of the river shoreline and
the access haul road along the top of the river
embankment.
Wednesday, October 31: Dow completed the
shoreline stabilization and restoration activities, and continued
the demobilization of equipment from the
Site.
|
|
The following tasks are soon to be
implemented:
• The decontamination and
demobilization of the wastewater treatment
equipment. • Reducing the temporary stone
access road to the Site from two lanes to one
lane • Complete restoration and planting
of native plants.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| RST/START |
$100,000.00 |
$67,600.00 |
$32,400.00 |
32.40% |
|
Intramural Costs
|
| |
| Total Site
Costs |
$100,000.00 |
$67,600.00 |
$32,400.00 |
32.40% |
* The above accounting of expenditures is an estimate based
on figures known to the OSC at the time this report was written. The OSC
does not necessarily receive specific figures on final payments made to
any contractor(s). Other financial data which the OSC must rely upon may
not be entirely up-to-date. The cost accounting provided in this report
does not necessarily represent an exact monetary figure which the
government may include in any claim for cost recovery.
|
As of 10/31/07, Dow has removed and transported to the landfill
approximately 16,398 in-place cubic yards of impacted sediment from
the Reach O site. A total of 911 loads, estimated at 18 in-place
cubic yards per load, have been transported to the Salzburg Landfill
for disposal. The following disposed waste dredged and disposed from
the Reach O area includes:
8/31/2007 6
loads 150 in-place
cubic yards 9/7/2007 84
loads 1,512 in-place cubic
yards 9/8/2007 174
loads 4,350 in-place cubic
yards 9/10/2007 33
loads 825 in-place cubic
yards 9/15/2007 71
loads 1,278 in-place cubic
yards 9/16/2007 76
loads 1,368 in-place cubic
yards 9/18/2007 164
loads 2,952 in-place cubic
yards 9/24/2007 162
loads 2,916 in-place cubic
yards 10/5/2007 77
loads 1,386 in-place cubic
yards 10/29/07 64
loads 1,152 in-place cubic yards
As of
10/31/07, Dow has treated and discharged approximately 63,444
gallons of water. The wastewater treatment process includes settling
and filtration using 25 and 10 micron filters. Samples are collected
continuously during the discharging process and tested for Total
Suspended Solids (TSS) and Total Equivalent (TEQ) concentrations of
dioxin and furans. The following quantity of water discharged from
the Reach O treatment operations
include:
9/14/2007 Batch
1 18,311 gallons
discharged 9/24/2007
Batch
2 7,953
gallons
discharged 10/4/2007
Batch 3 22,678
gallons
discharged 10/23/2007
Batch 4 14,502
gallons discharged
|
www.epaosc.net/TittabawasseeRiverReachO
|