|
United States Environmental
Protection Agency Region
V POLLUTION REPORT |
| Date: |
Thursday, September 13, 2007 |
| From: |
James Augustyn/Brian Schlieger, On-Scene
Coordinator |
| To: |
Jason El-Zein, USEPA |
David Chung, OSWER |
|
Al Taylor, MDEQ |
NRC Duty Officer, National Response
Center |
|
Cheryl Howe, MDEQ |
Rick Karl, USEPA |
|
Mark Johnson, U.S. EPA
R5 |
Todd Konechne, Dow Chemical
Company |
|
Jeff Cahn, USEPA |
Jim Sygo,
MDEQ |
|
Subject: |
Removal Action Tittabawassee
River Reach O Midland, MI Latitude:
43.5522 Longitude: -84.1714 |
| POLREP No.: |
4 |
Site #: |
B5KF |
| Reporting Period: |
8/31/07 to 9/12/07 |
D.O. #: |
|
| Start Date: |
8/13/2007 |
Response Authority: |
CERCLA |
| Mob Date: |
8/13/2007 |
Response Type: |
Time-Critical |
| Completion Date: |
|
NPL Status: |
Non NPL |
| CERCLIS ID #: |
MID980994354 |
Incident Category: |
Removal Action |
| RCRIS ID #: |
|
Contract # |
|
|
On June 27, 2007, U.S. EPA ordered The Dow Chemical Company (Dow)
to negotiate an Administrative Order on Consent, to address removal
of extremely elevated levels of dioxin-contaminated sediment from
within Reach O of the Tittabawassee River near Midland,
Michigan. Dow agreed to the terms of the Order and on
July 12, 2007, the Order was signed by the Regional Administrator
and Dow. For additional background information please see
the site profile.
On-Scene Coordinator (OSC) Jim Augustyn is
providing oversight with assistance from U.S. EPA’s START
Contractor, Weston Solutions, Inc. |
|
To view a map that depicts current site progress, please visit
the Document Section of this website and open the document titled
"Site features map".
The following tasks have been completed
by Dow’s contractor during the period from August 31 – September 12,
2007:
Friday, August 31st: Dow’s contractor began
installation of sheet piling around Removal Management Unit (RMU) 1
and 2 areas in the Tittabawasse River. Turbidity and spill control
countermeasures were installed in the river prior to the start of
work activities. Continuation of construction
activities on the dewatering and wastewater treatment pad. Sediment
dredged on August 29th was loaded into trucks and transported
off-site for disposal at the Salzburg Landfill.
Saturday,
Sept 1st: Dow’s contractor continued the installation of sheet
piling around RMU 1 and 2. Work continued on the ramp for access the
RMU 3 and 4 areas in the river. Continued work on the dewatering
/wastewater treatment pad.
Sunday, Sept 2nd and Monday, Sept
3rd: Installation of sheet piling around the perimeter of
the RMU 1 and RMU 2 continued.
Tuesday, Sept 4th: Dow’s
contractor completed the installation of sheet piling around RMU 1
and 2. Began dewatering, filtration, and discharge of
river water from the enclosed RMU 1 and 2 area. Work continued on
the ramp being constructed in order to access RMU 3 and RMU 4 areas
in the river. Continued construction work on the dewatering
/wastewater treatment pad.
Wednesday, Sept 5th: Dow’s
contractor continued the dewatering of RMU 1 and 2 areas to be
dredged. A dewatering trench was excavated within the enclosed RMU 1
and 2 areas in order to facilitate the dewatering of the sediments
within the sheet piling enclosure. Work continued on the ramp being
constructed in order to access the RMU 3 / 4 areas in the river.
Dow’s contractor began the installation of sheet piling around the
perimeter of the RMU 3 and 4. Turbid water was observed downstream
of the dewatering filtration operations. A review of the downstream
turbidity measurements indicated no exceedences. Dow’s contractor
implemented additional countermeasures to eliminate the downstream
turbid discharge.
Thursday, Sept 6th: Dow’s contractor began
the excavation of impacted sediment from RMU 1 and 2. Excavated
sediment was transported to the dewatering pad for staging.
Installation of sheet piling around the perimeter of the RMU 3 and 4
areas in preparation of the dredging activities
continued.
Friday, Sept 7th: Dow’s contractor
continued excavation of impacted sediment from RMU 1 and 2 areas.
Transportation and disposal of dewatered sediment to the Salzburg
Landfill began. Three of six post-removal samples were collected
from the northern portion of the RMU 1 / 2 areas and submitted for
laboratory analysis. Installation of sheet piling around the
perimeter of the RMU 3 and 4 areas continued.
Saturday, Sept
8th: Dow’s contractor completed the excavation of impacted sediment
in RMU 1 and 2 areas. Collection of the last three post-removal
samples from RMU 1 / 2 areas were collected and submitted to the
laboratory for analysis. Nine (9) post excavation sediment cores
were collected from the RMU 1 / 2 areas for visual characterization.
Installation of sheet piling around the perimeter of RMU 3 and 4
areas in preparation of the dredging activities
continued.
Sunday, Sept 9th: Site activities included the
continued dewatering of the RMU 1 / 2 dredge area cell, and the
modification of the haul road access ramp leading to the RMU 3 / 4
dredge area.
Monday, Sept 10th: Dewatering of RMU 1 / 2 areas
continued. Post-removal GPS coordinates and elevations of RMU 1 / 2
excavation areas were collected. Installation of sheet piling around
the perimeter of the RMU 3 and 4 areas continued.
Tuesday,
Sept 11th: Dow’s contractor has completed the installation of the
sheet piling around the RMU 3 excavation area. The
dewatering process of RMU 3 area started during the night shift
operation.
Wednesday, Sept 12th: Dewatering operations
continued at the RMU 3 excavation area in preparation for sediment
excavation activities. Dow’s contractor started the installation of
sheet piling around the perimeter of the RMU 4 area.
The
following tasks are currently on
going:
• The collection of turbidity
measurements from meters in the Tittabawassee River in order to
compare downstream turbidity measurements with background
turbidity. • Continued dewatering of the
RMU 3 / 4 excavation area. • The review of
laboratory analysis from the post excavation samples collected from
the RMU 1 / 2 areas. • The installation of
sheet piling around the perimeter of the RMU 4
area. • Pumping and storage of wastewater
from the dewatering pad into Baker
tanks.
|
|
The following tasks will be
implemented:
• The excavation of
impacted sediments from RMU
3. • Transportation and disposal of the
impacted sediment to Salzburg
Landfill. • Treatment and discharge of
water generated from the impacted sediment dewatering operations.
• The removal of the sheet piling from
the RMU 1 / 2 areas.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| RST/START |
$100,000.00 |
$27,700.00 |
$72,300.00 |
72.30% |
|
Intramural Costs
|
| |
| Total Site
Costs |
$100,000.00 |
$27,700.00 |
$72,300.00 |
72.30% |
* The above accounting of expenditures is an estimate based
on figures known to the OSC at the time this report was written. The OSC
does not necessarily receive specific figures on final payments made to
any contractor(s). Other financial data which the OSC must rely upon may
not be entirely up-to-date. The cost accounting provided in this report
does not necessarily represent an exact monetary figure which the
government may include in any claim for cost recovery.
|
As of 9/12/07, Dow has removed and transported to the landfill
approximately 6,837 in-place cubic yards of impacted sediment from
the Reach O site. A total of 297 loads, estimated at 25 cubic yards
per load, have been transported to the Salzburg Landfill for
disposal.
8/31/2007 6
loads 150 in-place cubic
yards 9/07/2007 84
loads 1,512 in-place cubic
yards 9/08/2007 174
loads 4,350 in-place cubic
yards 9/10/2007 33
loads 825 in-place cubic
yards
|
epaosc.net/TittabawasseeRiverReachO
|