|
United States Environmental
Protection Agency Region
V POLLUTION REPORT |
| Date: |
Monday, October 29, 2007 |
| From: |
James Augustyn/Brian Schlieger, On-Scene
Coordinator |
| To: |
Jason El-Zein, U.S. EPA |
David Chung, U.S.
EPA |
|
Duty Officer, USCG |
Al Taylor, MDEQ |
|
Cheryl Howe, MDEQ |
Jeff Cahn, U.S. EPA |
|
Rick Karl, USEPA |
Mark Johnson, U.S. EPA
R5 |
|
Steve Lucas, Dow Chemical
Company |
Jim Sygo, MDEQ |
|
Mark Durno, USEPA |
|
|
Subject: |
Tittabawassee River Project - Reach
D Tittabawassee River Dioxin-Reach
D Midland, MI Latitude: 43.6011 Longitude: -84.2386
|
| POLREP No.: |
14 |
Site #: |
B5KF |
| Reporting Period: |
10-16-07 thru 10-24-07 |
D.O. #: |
|
| Start Date: |
7/9/2007 |
Response Authority: |
CERCLA |
| Mob Date: |
7/9/2007 |
Response Type: |
Time-Critical |
| Completion Date: |
|
NPL Status: |
Non NPL |
| CERCLIS ID #: |
MID980994354 |
Incident Category: |
Removal Action |
| RCRIS ID #: |
|
Contract # |
|
|
On July 9, 2007, Dow’s contractor began positioning equipment on
a work barge to begin the preparation of driving temporary sheet
piling in the river to delineate the area of highest dioxin
contamination. Dow’s contractor has completed
construction on the HDPE sediment transport pipeline and has
conducted hydrostatic testing of the line. The sediment transport
line is approximately 9,000 feet long and will transport sediment
slurry from the dredge area in the river to the Geo-Tube dewatering
cell.
On-Scene Coordinator (OSC) Jim Augustyn is providing
oversight with assistance from U.S. EPA’s START Contractor, Weston
Solutions, Inc. |
|
The following activities have been completed by Dow during the
period of October 16th through October 24th. Routine
tasks such as dredging, raking of debris, excavation of sediment
within contained turbidity barrier, stockpiling and dewatering of
sediment, air monitoring, turbidity data collection and 24-hour
composite water sampling from the settling pond for total suspended
solids (TSS) analysis are performed daily.
To view an aerial
photo that depicts current site progress, please visit the Document
Section of this website and open the document titled "Reach D
Project Progress Figure".
October 16th, Dow completed
installation of permanent sheet piling from the dam to the 36” water
main and continued the excavation of gravel, wood and debris within
the middle containment cell. Contractors collected the 39th 24-hour
composite sample for TSS analysis. The 24 hour discharge
volume for 10/15/08 to 10/16/07 was 422,547
gallons.
October 17th, Dow continued excavation
activities within the middle containment cell and conducted a
quality control (QC) survey of the middle cell to determine
remaining quantity of sediment for
dredging/excavation.
October 18th, Dow installed
a sheet piling ‘cut-off’ wall within the southern containment cell
between what will be the 30” water main cell and the final cell and
continued the driving of permanent sheet piling from the dam to the
36” water main. Excavation and stockpiling activities
continued within the middle containment cell along with beginning
vacuum dredging activities.
October 19th, Divers were on
site to perform under water cutting of the historic flume piling
immediately adjacent to the 36” water main. A total of 14 sheets
were cut-off at the riverbed elevation including those directly over
the pipe. Divers also inspected the turbidity curtain
installations over each water main. Vacuum dredging and
load out of gravel and debris continued within the middle
containment cell along with the driving of permanent sheet piling.
October 20th, Dow continued vacuum dredging and load out
activities from within the middle containment cell. Torch
cut permanent sheet piling that had been driven to ‘ultimate
refusal’, and re-anchored the turbidity curtain over the 30” water
main.
October 22nd, Dow completed vacuum dredging activities
and performed a final QC survey within the middle containment cell,
continued torch cutting of temporary sheet piling to grade and
completed the anchoring of the turbidity curtain over the 30” and
36” water main.
October 23rd, Dow installed
permanent sheet piling within a trench shield around the 36” water
main. Contractors conducted a hydrographic survey to
determine dredge quantities and establish a dredging matrix prior to
beginning dredge operations within the 30” water main cell
immediately south of the middle containment cell. START
collected split samples for laboratory analysis of post-removal
sampling within the middle containment cell.
October 24th,
Dow completed installation activities of permanent sheet piling
across the 36” water main, continued dredge operations within the
30” water main cell area and conducted a post dredge survey within
the cell.
October 25th thru October 27th Contractors
continued dredge operations within the 30” water main cell, began
demobilization of equipment and personnel, conducted QC surveys
within the 30” water main cell and completed load-out of gravel and
debris from the dewatering
stockpile.
|
|
Dow’s contractors will continue dredge and excavation operations
within 30” water main cell and then concentrate efforts on the
remaining final cell.
Prior to initiation of
final cell dredge operations, completion of temporary turbidity
barrier sheet piling will be completed immediately north of the 36”
water main
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| RST/START |
$160,000.00 |
$92,000.00 |
$68,000.00 |
42.50% |
|
Intramural Costs
|
| |
| Total Site
Costs |
$160,000.00 |
$92,000.00 |
$68,000.00 |
42.50% |
* The above accounting of expenditures is an estimate based
on figures known to the OSC at the time this report was written. The OSC
does not necessarily receive specific figures on final payments made to
any contractor(s). Other financial data which the OSC must rely upon may
not be entirely up-to-date. The cost accounting provided in this report
does not necessarily represent an exact monetary figure which the
government may include in any claim for cost recovery.
|
To date, approximately 398 pieces (average length 10 to 12 feet)
of historic flume piling have been extracted from the Reach D
project area. The flume piling will be decontaminated and
processed for metal reclamation.
Waste consisted of Reach D
rip-rap, misc. debris and sediment. A total of 578 loads, estimated
at 12 cubic yards per load total volume 6,936 estimated cubic
yards
7-31-07, 34
loads 8-01-07, 35
loads 8-02-07, 39
loads 8-03-07, 24
loads 8-04-07, 11
loads 9-07-07, 04
loads 9-08-07, 07
loads 9-17-07, 17
loads 9-18-07, 16
loads 9-19-07, 15
loads 9-20-07, 23
loads 9-24-07, 15
loads 9-26-07, 22
loads 9-28-07, 24
loads 10-02-07, 13
loads 10-03-07, 13 loads 10-04-07, 15
loads 10-05-07, 21
loads 10-08-07, 23
loads 10-09-07, 21 loads 10-10-07, 22
loads 10-11-07, 22
loads 10-12-07, 17
loads 10-15-07, 36 loads 10-16-07, 04
loads 10-17-07, 18
loads 10-19-07, 31
loads 10-20-07, 02 loads 10-24-07, 13
loads 10-25-07, 07
loads 10-26-07, 06
loads 10-27-07, 08 loads
From 9-06-07
to 10-27-07 Reach D sediment dewatering activities have conveyed
31,553,252 gallons of water to Dow's waste water treatment plant
(WWTP).
|
www.epaosc.net/tittabawasseeDioxinReachD
|