|
United States Environmental
Protection Agency Region
V POLLUTION REPORT |
| Date: |
Friday, August 10, 2007 |
| From: |
James Augustyn/Brian Schlieger, On-Scene
Coordinator |
| To: |
Bill Bolen, U.S. EPA |
Jason El-Zein, U.S.
EPA |
|
David Chung, U.S. EPA |
Duty Officer, USCG |
|
Al Taylor, MDEQ |
Cheryl Howe, MDEQ |
|
Jeff Cahn, U.S. EPA |
Rick Karl, USEPA |
|
Mark Johnson, U.S. EPA
R5 |
Steve Lucas, Dow Chemical
Company |
|
Subject: |
Tittabawassee River Project - Reach
D Tittabawassee River Dioxin-Reach
D Midland, MI Latitude: 43.6011 Longitude: -84.2386
|
| POLREP No.: |
4 |
Site #: |
B5KF |
| Reporting Period: |
8-04-07 to 8-09-07 |
D.O. #: |
|
| Start Date: |
7/9/2007 |
Response Authority: |
CERCLA |
| Mob Date: |
7/9/2007 |
Response Type: |
Time-Critical |
| Completion Date: |
|
NPL Status: |
Non NPL |
| CERCLIS ID #: |
MID980994354 |
Incident Category: |
Removal Action |
| RCRIS ID #: |
|
Contract # |
|
|
On July 9, 2007, Dow’s contractor began positioning equipment on
a work barge to begin the preparation of driving temporary sheet
piling in the river to delineate the area of highest dioxin
contamination. Dow’s contractor has completed
construction on the HDPE sediment transport pipeline and has
conducted hydrostatic testing of the line. The sediment transport
line is approximately 9,000 feet long and will transport sediment
slurry from the dredge area in the river to the Geo-Tube dewatering
cell.
On-Scene Coordinators (OSC) Jim Augustyn and Brian
Schlieger are providing oversight with assistance from U.S. EPA’s
START Contractor, Weston Solutions,
Inc.
|
|
The following tasks have been completed by Dow’s contractors
during the period of August 04 to August 9th, 2007:
Saturday
8-04-07: Installation and driving of the temporary sheet piling
turbidity barrier continued in the river and excavation and disposal
of rip rap to Dow’s Salzburg Landfill continued. Air
monitoring throughout the project area continued. Dow’s
contractor continued collecting background turbidity data from
turbidity monitors located upstream and downstream of the project
area. Work activities at the containment site includes;
installation of wood walkway and sampling platform, electrical, HDPE
discharge pipe fabrication, site restoration, and dust and track-out
control.
Monday 8-06-07: Installation and driving of the
temporary sheet piling turbidity barrier continued in the river,
along with the removal of temporary sheet piling at the upstream
portion of the turbidity barrier to allow access for a construction
barge. Air monitoring throughout the project
area continued. Dow’s contractor continued collecting
background turbidity data from turbidity monitors located upstream
and downstream of the project area. Dow contractors made
temporary modifications to HDPE Sediment Transport dredge line at
booster station #1 located on Eastern bank within turbidity
barrier. Additional Reach D activities included the
staging of sheet metal piling, pump setup, delivery of equipment and
materials. Work activities at the containment cell
continued with the addition of the installation of PVC odor control
piping.
Tuesday 8-07-07: Installation and driving
of the temporary sheet piling turbidity barrier continued in the
river. Dow contractors removed sufficient amount of
temporary sheet piling to allow access for construction barge inside
the turbidity barrier. Air monitoring throughout the
project area continued as well as turbidity data
collection. Work activities at the containment site
continued with the off loading of equipment and materials,
electrical, pump storm water to plant sewers, geo-tube header pipe
assembly, building pad site layout, and dust and track-out
control.
Wednesday 8-08-07: Installation and
driving of the temporary sheet piling turbidity barrier continued in
the river. Dow contractors began removing historic sheet
metal piling within the turbidity Northern section. Air
monitoring throughout the project area continued as well as
turbidity data collection. Work activities at the
containment cell continued.
Thursday
8-09-07: Installation and driving of the temporary sheet
piling turbidity barrier continued in the river. Dow
contractors continued the removal of historic sheet metal piling
from within the turbidity barrier. Air monitoring
throughout the project area continued as well as turbidity data
collection. Work activities at the containment cell
continued.
|
|
Sheet piling will be driven down to established elevations to
complete the installation of the turbidity barrier between the Dow
bridges and downstream of the Dow’s ‘railroad’
bridge.
Removal of historic flume sheet piling will continue
from within the turbidity barrier.
Permanent sheet piling
will be driven along the RGIS System.
Permanent turbidity
monitors will be placed in the river to monitory potential increases
in turbidity that may result from excavation and dredging
operations.
Construction on the containment cell will
continue. Geo-Tubes and associated connections to the
sediment transport line will be completed in preparation for
dredging operations to start.
|
|
Once all remaining large debris and rip-rap is removed the
installation of new permanent sheet piling for the RGIS system will
begin. Dredging of contaminated sediment cannot begin
until the permanent sheet piling is in place.
A
third sheet piling crew will be mobilized to the
site. Two other piling crews will continue to install
temporary sheet piling along the entire length of the project area
and will end adjacent to the Dow
Dam.
|
|
On Thursday evening August 9th, USEPA participated in the
Community Meeting cosponsored by MDEQ and Dow Chemical in Saginaw,
MI. |
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| RST/START |
$120,000.00 |
$28,000.00 |
$92,000.00 |
76.67% |
|
Intramural Costs
|
| |
| Total Site
Costs |
$120,000.00 |
$28,000.00 |
$92,000.00 |
76.67% |
* The above accounting of expenditures is an estimate based
on figures known to the OSC at the time this report was written. The OSC
does not necessarily receive specific figures on final payments made to
any contractor(s). Other financial data which the OSC must rely upon may
not be entirely up-to-date. The cost accounting provided in this report
does not necessarily represent an exact monetary figure which the
government may include in any claim for cost recovery.
|
Waste consisted of Reach D rip-rap from the RGIS
system. A total of 143 loads, estimated at 12 cubic yards
per load total volume 1,716 estimated cubic yards
7-31-07, 34
loads 8-01-07, 35 loads 8-02-07, 39 loads 8-03-07, 24
loads 8-04-07, 11 loads |
epaosc.net/tittabawasseeDioxinReachD
|